Infrastructure rebuild to 2016, map and details released today

Printer-friendly version

The schedule for the rebuild of Christchurch’s earthquake-damaged roads and underground services was released today by the Minister for Canterbury Earthquake Recovery Gerry Brownlee and Christchurch Mayor Bob Parker.

The plan includes a map setting out indicative timeframes for infrastructure repairs in different areas of the city. The work has been prioritised based on a range of factors, with the aim being to first fix the worst-affected areas that impact on the most people.

“This work is one piece of a much bigger and complex city-wide recovery programme,” says Minister Brownlee. “But it is highly significant as underground services need to be rebuilt and future-proofed so that the city’s recovery is founded on a secure infrastructure base.

“It will take another four years to rebuild Christchurch’s horizontal infrastructure and deciding what comes first is not easy. We’ve used a robust model to prioritise the work and that’s what we’re launching today. Of course, things might change as work progresses, but residents can now have a good idea of when we’ll be working in their neighbourhood.”

Mayor Parker says the works schedule underpins confidence in the city’s recovery and reinvestment in the South Island’s largest city.“People will begin to see a more resilient and forward-looking city emerging from the legacy of the earthquakes,” he says. “The schedule we are launching today gives certainty for the future; but we have already made good progress on the rebuild and work has been ongoing for more than a year now.

“Already, we’ve completed 187 projects worth $73 million including: rebuilding 39km of wastewater pipe – that’s about the distance from central Christchurch to Dunsandel – and laying 92,000 square metres, or 13 rugby fields, of road pavement.”

SCIRT, the Stronger Christchurch Infrastructure Rebuild Team, is a partnership that has been formed to deliver the infrastructure rebuild. The New Zealand Government and Christchurch City Council are leading and funding the rebuild, which is being delivered in partnership with five key construction contractors.

Details of projects set to begin construction in the next six months are also available on the SCIRT website (button top right hand corner Road to Recovery) and will be updated quarterly.

The site for today's schedule release was Bexley Reserve, Pages Road, Wainoni, where a new wastewater pump station is being built by SCIRT partner Fulton Hogan.

 

Mayor Bob Parker and Canterbury Earthquake Recovery Minister Gerry Brownlee  at today’s release of the SCIRT work schedule at Bexley Reserve, the site for a major new pump station.

 

 

Published: 07 September 2012