Moorhouse Avenue - Addington / Central city - Roading - wastewater - storm water and freshwater repairs

Printer-friendly version
What
Repairing the road carriageway and service pipes in the ground.
When
Week beginning Monday 21 November 2016 until end of March 2017.
Where
Moorhouse Avenue, west of the Antigua Street intersection.
Traffic
Two lanes of traffic will be maintained on Moorhouse Avenue in both directions.

Map 1: Location of works.
Map 1. Work site (yellow): Moorhouse Avenue (adjacent west of Antigua Street) work will be done in four stages maintaining traffic flow.
Sourced from LINZ data, Crown Copyright reserved.

What we are doing

  • Downer, as part of SCIRT, is repairing the earthquake damaged road, wastewater, storm water and freshwater pipes in a section of Moorhouse Avenue, see Map 1 for location of work.
  • Stage one will start during the week starting Monday 21st November.
  • Stage two, three and four will start on the completion of the previous stage.
  • Due to the poor ground conditions in this section of road an extensive full road reconstruction to a depth of 850mm is needed. This involves digging out the road and building up a strong resilient base.
  • Work will be done in stages to maintain a minimum of two lanes of traffic in both directions on Moorhouse Avenue at all times.
  • Stage one and two will be on the north side of Moorhouse Avenue.
  • Stage three and four will be on the south side of Moorhouse Avenue and will start in the new year.
  • Work is subject to favourable weather and on-site conditions and is expected to be completed by end of March 2017.

Need more information?

Call Downer on:
0800 400 310 between 8.30am and 5.00pm Monday to Friday
Email Downer:
[email protected]
Visit the SCIRT website:
www.strongerchristchurch.govt.nz

Map 2: Stage one traffic management, and Map 3: Stage two traffic management. Sourced from LINZ data, Crown Copyright reserved. Worksite (blue): Stage 1 southern side of the northern side of Moorhouse Avenue (adjacent west of Antigua Street), Stage 2 northern side of the northern side of Moorhouse Avenue (adjacent west of Antigua Street); Traffic management (red): Stage 1 southern side of the northern side of Moorhouse Avenue (adjacent west of worksite), Stage 2 northern side of the northern side of Moorhouse Avenue (adjacent west of worksite); Traffic flow (yellow arrows): Stage 1 two lanes eastwards along Moorhouse Avenue (passing the northern side of traffic management/work area to the intersection with Antigua Street) and two lanes weswtwards along Moorhouse Avenue (to the intersection with Antigua Street), Stage 1 two lanes eastwards along Moorhouse Avenue (passing the southern side of traffic management/work area to the intersection with Antigua Street); No right turn: from Antigua Street into Moorhouse Avenue, from Moorhouse Avenue (westwards) into Antigua Street (northwards).
Sourced from LINZ data, Crown Copyright reserved.

Traffic Impacts

  • During stage one and two work will be on the north side of Moorhouse Avenue, see Map 2 and Map 3.
  • Two lanes will be maintained for eastbound traffic.
  • There will be a 30km/h speed limit around the work site.
  • There may be no right turns out of and into Antigua Street.
  • There will be no on-street parking around the site.

Work hours will generally be during the day. Night works may occur later in the project.

General Information

  • Our standard work hours are Monday to Saturday between the hours of 7.00am to 6.00pm. All works are subject to favourable weather and on-site construction conditions.
  • There will be increased noise, dust and vibration levels associated with this work.
  • Safety is our number one priority. Safety is your responsibility too. Stay clear and stay alert—keep children and pets at a safe distance from the work site.

Start date: 
Mon, 21/11/2016
Project numbers: 
11264