Reserve Terrace - Lyttelton - Water main reinstatement

Printer-friendly version
What
Water main relay and lateral connections.
When
Starting within the week of Monday 28 November 2016 for about two weeks.

Map 1: Stage 1 works. Worksite (blue) and road closed: Reserve Terrace (between 31 and Randolph Terrace, where 31 is north of the intersection with Randolph Terrace).
Sourced from LINZ data, Crown Copyright reserved.

We understand the impacts of this work are significant. Please contact the Downer team if you have any questions or concerns. Thank you for your patience while we complete these essential repairs.

What we are doing

  • Downer, as a part of SCIRT, is repairing earthquake damaged, publicly owned retaining walls on Reserve Terrace in Lyttelton.
  • Repairs to the retaining walls are almost complete. For the past two weeks we have been installing drainage at the back of the newly installed retaining walls.

Stage 1 works

  • On Tuesday 29 November, for about two–four days, subject to favourable on-site and weather conditions, we will begin relaying the water main along Reserve Terrace. See Map 1 for location of works.
  • During this stage of works,vehicle access to properties 29B, 27, 23, 17, 16, 14, 13, 12, and 10 Reserve Terrace will be restricted.
  • Property number 49 Sumner Road will lose vehicle access on Tuesday 29 November for one day only.
  • A turning bay will be available at our site office on the Reserve Terrace and Sumner Road junction.
  • Pedestrian access will be maintained for resident access only.

Map 2: Stage 2 works. Worksite (orange): Reserve Terrace (between 12/29B to and through the intersection with Watsons Lane; 12 and 29B are south of Watsons Lane) and Watsons Lane (between Reserve Terrace and St Davids Street), western side of Reserve Terrace (between 23 and 29B, and between Randolph Terrace and 17; these are all between Randolph Terrace and Watsons Lane); No-parking cones (blue dashed): Reserve Terrace (between Randolph Terrace and 17); No entry (red discs): Watsons Lane (at St Davids Street, at Reserve Terrace, at Randolph Terrace); Designated parking spots (yellow discs): eastern side of Reserve Terrace (between 10 and 12, which are near to but north of the intersection with Randolph Terrace), and northeastern side of St Davids Street (at 31, which is adjacent southeast of Watsons Lane).
Sourced from LINZ data, Crown Copyright reserved.

Stage 2

  • Following the completion of stage 1 works, we will complete the water main relay and connection at Watsons Lane.
  • This work is expected to take about one week to complete, subject to favourable on-site and weather conditions.
  • Watsons Lane will be closed to pedestrians for this stage of work. The suggested detour route to the Town Centre will be via Randolph Terrace, Stevensons Steep, and St Davids Street.
  • Residents at properties 14, 16, 29B, 31, and 33 Reserve Terrace; and 31 Sumner Road will have restricted vehicle access to properties at times during this stage of works. See Map 1 for designated parking spots.
  • Vehicles parked within the worksite are advised to reverse down into Reserve Terrace from the Randolph Terrace and Reserve Terrace junction. Vehicles can turn around at our site office on the Reserve Terrace and Sumner Road junction.
  • Pedestrian access to properties will be maintained for resident access only.

Upcoming works

  • Following the completion of these two stages of works we will begin road reinstatement works along Reserve Terrace.
  • You will receive a work notice before this work begins.

General Information

  • Please contact Downer on 0800 400 310 if you have any specific access requirements that we need to consider e.g. large vehicle deliveries, rubbish collection, or planned works on your property.
  • Our work hours are Monday to Friday between the hours of 7.00am and 6.00pm. On occasion we may need to work during the weekend to complete essential work.
  • There will be increased noise, dust and vibration levels associated with this work.

Need more information?

Contact Downer on 0800 400 310 or [email protected]

Start date: 
Mon, 28/11/2016
Project numbers: 
10426