Hampshire Street - Aranui - partial road repair *Update*

Printer-friendly version
Hampshire Street (between Breezes Road and 18 Hampshire Street): Further to the update notice you may have received on 18 November 2016, this note is to advise you that sealing of the road along this section of Hampshire Street is scheduled for next week. Final reinstatement of the berms and hydro seeding of the grass will also be underway over the next two weeks.

This notice is an update for an earlier notice.

Traffic impact

The temporary road closure will remain in place until all the roading work is complete. Please be on the lookout for changed traffic conditions.

Fletcher Infrastructure, on behalf of SCIRT, would like to take this opportunity to thank residents, for your patience, support and cooperation while this work is underway in your street.

Thanks | Kia Ora | Fa'afetai.

  • Talk to us at Fletcher on 0800 444 919
  • Contact us

Sealing on the road—General Information

  • Sealing of the road is subject to favourable weather conditions.
  • On-street parking outside your property will not be available during this work. If you do not have off-street parking, please park your vehicle away from the work zone, so the work can be completed promptly and with minimal disturbance to residents and other road users.
  • After application, the bitumen remains soft and may stick to your tyres or paint work. We advise you to remove this ASAP to prevent further damage.
  • The surfacing treatment will be a "Chip Seal" finish. As a result there will be loose chip on the road. Please reduce your speed in these areas to prevent loose chips from flying up.
  • Please keep young children and animals well supervised and clear of the work area.
  • The road closure will be uplifted when the work is completed.
Start date: 
Fri, 09/12/2016
End date: 
Fri, 23/12/2016
Project numbers: 
11074