Moorhouse Avenue - Addington / Central city - Roading - wastewater - storm water and freshwater repairs - End of Year

Printer-friendly version
Where: Moorhouse Avenue, west of the Antigua Street intersection.

Map 1: Location of works. Stage 1 worksite (yellow): southern side of the northern side of Moorhouse Avenue (adjacent west of Antigua Street); Stage 2 worksite (purple): northern side of the northern side of Moorhouse Avenue (adjacent west of Antigua Street); Stage 3 worksite (blue): northern side of the southern side of Moorhouse Avenue (adjacent west of Antigua Street); Stage 4 worksite (red): southern side of the southern side of Moorhouse Avenue (adjacent west of Antigua Street).
Sourced from LINZ data, Crown Copyright reserved.

What we are doing

  • Downer, as part of SCIRT, is repairing the earthquake damaged road, wastewater, storm water and freshwater pipes in a section of Moorhouse Avenue.
  • Within the week of Monday 19 December 2016, we will lay a temporary road seal on the Stage 1 section of road. See Map 1 for location of works.
  • Once sealed, the lane drop for eastbound traffic will be removed. Traffic flow will be restored to normal on Moorhouse Avenue over our Christmas and New Year's shut-down period.

SCIRT will shut down this worksite from Friday 23 December 2016 to Monday 16 January 2017, over the Christmas and New Year's break.

SCIRT would like to thank you for your patience throughout 2016.

Have a safe and happy festive season.

Upcoming works

Stage 2 repairs

  • Work will recommence on Monday 16 January 2017 in the Stage 2 worksite. See Map 2 for location of works.
  • During this stage we will be reconstructing the carriageway. Due to the poor ground conditions, a full dig out of 850mm will be done.
  • Two lanes will be maintained for eastbound traffic.
  • There will be a 30km/hr speed limit around the work site.
  • There will be no right turns across the Moorhouse Avenue and Antigua Street intersection.
  • There will be no on-street parking around the site
  • Work hours will generally be during the day. Night works may occur later in the project.

Map 2: Stage 2 worksite. Stage 2 worksite (purple): northern side of the northern side of Moorhouse Avenue (adjacent west of Antigua Street and in the westerns die of the intersection with Antigua Street); Reduced eastbound traffic flow (blue arrows): two lanes eastwards along Moorhouse Avenue (passing the southern side of the worksite to the intersection with Antigua Street); No right turn: from Antigua Street into Moorhouse Avenue, from Moorhouse Avenue into Antigua Street.
Sourced from LINZ data, Crown Copyright reserved.

Stage 3 and 4 repairs

  • Following the completion of Stage 1 and 2 repairs, we will move to the south side of Moorhouse Avenue. See Map 1 for location of works.
  • We will deliver another work notice before this work begins.

General Information

  • Please contact Downer on 0800 400 310 if you have any specific access requirements that we need to consider e.g. large vehicle deliveries, rubbish collection, or planned works on your property.
  • Our work hours are Monday to Friday between the hours of 7.00am and 6.00pm. On occasion we may need to work during the weekend to complete essential work.
  • There will be increased noise, dust and vibration levels associated with this work.
  • Works will have no planned impact on current power, telecommunication, water or gas services. However, the network is still fragile so please be prepared in case there is an unexpected service cut off.
  • Safety is our number one priority. Safety is your responsibility too. Stay clear and stay alert—keep children and pets at a safe distance from the worksite.

Need more information?

Contact Downer on 0800 400 310 or [email protected]

Start date: 
Mon, 19/12/2016
Project numbers: 
11264