Mt Pleasant Road - Mt Pleasant - Retaining wall repairs - Completion

Printer-friendly version
Works end. Thank you.
  • Downer as part of SCIRT has been working on Mt Pleasant Road since September 2015 repairing the earthquake damaged retaining wall and completing minor road and footpath repairs.
  • The work has progressed very well and we are pleased to inform you that the repairs to the retaining walls as well as the other associated repairs have been completed.
  • There are a few minor repairs to the road surface to complete over the next 3–4 weeks.
  • Reconstructing the earthquake damaged retaining wall has taken many months and many people to complete.

This project in numbers

  • We have repaired 60m of stone wall
  • Used 46m² of shotcrete
  • Installed 56×3.5m long anchors through the existing wall
  • Repaired 170m² of new footpath, and 100m of kerb and channel.
  • Diverted the water main and installed a new pipe.
  • Replaced 110m of pedestrian barrier.

The footpath and capping beam

Three photographs (before | during | after ) of footpath and capping beam.

Retaining wall beside #69 Mt Pleasant Road

Two photographs of retaining wall, One before repairs, the other after.

Retaining wall beside #93 Mt Pleasant Road

Two photographs of retaining wall, One during repairs, the other after.

SCIRT's allocated work programme will be completed by December 2016. However, this is not the end of the rebuild programme. After this, Council and the Transport Agency will continue to repair and rebuild the remaining damaged infrastructure. The Council's Long Term Plan incorporates an extensive Council-led multi–million dollar recovery programme that continues the work for 30 years.

89%

We are 89% through the SCIRT programme.

Need more information

Contact Downer on 0800 400 310 or [email protected]

Start date: 
Sun, 01/05/2016
Project numbers: 
10566