Godley Quay - Lyttelton - water main replacement

Printer-friendly version
What
Replace the earthquake damaged water main
Where
Godley Quay, between Cyrus Williams Quay and Voelas Road
When
From Monday 6 June for around three months

Where

Map. Watermain replacement (blue): Godley Quay (between Cyrus William Quay and Voelas Road).
Sourced from LINZ data, Crown Copyright reserved.

What we're doing

The earthquake damaged water main on Godley Quay needs to be replaced. This is an extensive job that will take around three months to complete.

The work will be done in sections to limit the amount of people we are affecting at one time. We will be beginning at the northern end of Godley Quay and moving south towards Cyrus Williams Quay. When working directly in front of properties vehicle access to driveways will be unavailable during working hours.

Where possible we will make access available to driveways at night.

Traffic lights will be used to maintain two-way traffic at all times.

What to expect

A trench being dug by machinery surrounded by fencing.

Machinery, and a worker in a trench, surrounded by mounds of earth and road cones.

Workers, and machinery in a trench containing pipes, separated from a road lane by road cones.

Example of traffic impact

Traffic lights will be in place maintaining traffic in both directions. Please be on the look out as our worksite progresses further down the street. Pedestrian access will be available past the worksite and to properties at all times. Parking will not be available directly next to our worksite.

Map. Work site (red): part of the northwestern side of Godley Quay (near to but southwest from Voelas Road); Traffic flow (black arrows): northeast/southwest along Godley Quay (passing the southeastern side of the worksite); Traffic lights (green/amber/red): adjacent to each end of the work site.
Sourced from LINZ data, Crown Copyright reserved.

General Information

  • Please contact Fulton Hogan on 0800 277 3434 if you have any specific access requirements that we need to consider e.g. nurse/doctor visits, Meals on Wheels, or planned works on your property.
  • Our standard work hours are Monday to Friday between the hours of 7.00am to 6.00pm.
  • There will be increased noise, dust and vibration levels.
  • Works will have no planned impact on current power, telecommunication, water or gas services. However, the network is still fragile so please be prepared in case there is an unexpected service cut off.
  • All works are subject to favourable weather and on-site construction conditions.
  • Safety is our number one priority. Safety is your responsibility too. Stay clear and stay alert—keep children and pets at a safe distance from the work site.

Need more information?

Call Fulton Hogan on:
0800 277 34 34 (8.30am–5.00pm Monday–Friday)
Email Fulton Hogan:
rebuildinfo@fultonhogan.com
Visit the SCIRT website:
www.strongerchristchurch.govt.nz

Start date: 
Mon, 06/06/2016
End date: 
Fri, 09/09/2016
Project numbers: 
11063