Fitzgerald Avenue Twin Bridges - Richmond / Linwood / Central city - Wastewater - bridge and roading repairs - Overview

Printer-friendly version
What
Replacement of wastewater main pipe, restoration of handrails on the Twin Bridges, and resurfacing of roading around the bridges.
When
Starting the week of Monday 27 June, 2016 for about three months.

Map 1: Location of Works. Sourced from LINZ data, Crown Copyright reserved. Wastewater repairs (orange): eastern side of the western side of Fitzgerald Avenue (between Kilmore Street and River Road), western side of the eastern side of Fitzgerald Avenue (between  River Road and Avonside Drive); Roading repairs (bright green): intersection of Fitzgerald Avenue (with River Road), intersection of Fitzgerald Avenue (with Avonside Drive/Kilmore Street); Kerb and footpath repairs (blue): western side of the western side of Fitzgerald Avenue (between Kilmore Street and River Road) and southwestern corner of Fitzgerald Avenue/River Road and northwestern corner of Fitzgerald Avenue/Kilmore Street), eastern side of the eastern side of Fitzgerald Avenue (between River Road and Avonside Drive) and southeastern corner of Fitzgerald Avenue/River Road and northeastern corner of Fitzgerald Avenue/Avonside Drive; Handrail repairs (pink): eastern side of the western side of Fitzgerald Avenue (between Kilmore Street and River Road), western side of the eastern side of Fitzgerald Avenue (between River Road and Avonside Drive),  western side of the western side of Fitzgerald Avenue (adjacent south of River Road), eastern side of the eastern side of Fitzgerald Avenue (adjacent south of River Road).

What we are doing

  • Downer as part of SCIRT will be doing wastewater repairs on the Fitzgerald Avenue Twin Bridges. Refer to Map 1 for location of work.
  • We will be replacing the wastewater mainline that currently runs above the ground alongside of the bridge.
  • We will be conducting repairs to the bridge handrails.
  • The road, kerb and footpaths that run alongside the Twin Bridges will be resurfaced.
  • Work will start during the week of Monday 27 June 2016 and take approximately three months to finish, subject to favourable weather and on-site conditions.

Traffic impacts

  • There are six stages in Traffic Management during the works. Please refer to Map 2 and Map 3 for Stage 1 and Stage 2 of the works. You will receive prior notification before any changes in traffic management occur.
  • Two-way traffic on Fitzgerald Avenue will be maintained across the Twin Bridges during the works.
  • Access to footpaths will be closed while we make repairs to the handrails. Pedestrian access across the bridge will be maintained at all times.
  • Access to properties and businesses will be maintained at all times.
  • Please be alert to changes in traffic management, follow signage and drive to the changed conditions.
  • Cones and signs are essential to allow our workers to safely complete the work. Traffic management is a legal requirement.

Stage 1 Works

  • Stage 1 works will start on Monday 27 June, 2016 and continue for about 3 weeks.
  • During Stage 1 the wastewater pipe will be installed North of the Twin Bridges. Refer to Map 2 for location of works.
  • Temporary scaffolding will be placed in the Avon River underneath the Twin Bridges.
  • Two-way traffic will be maintained on Fitzgerald Avenue across the Twin Bridges. There will be no-parking cones in place alongside the worksite.
  • Please follow signage on-site and drive to the changed conditions.

Map 2: Stage 1
Map 2. Worksite (bright green): centre of Fitzgerald Avenue (between Avonside Drive/Kilmore Street to and through the intersection with River Road); No-parking cones (orange dashed): southeastern side of Fitzgerald Avenue (adjacent northeast of River Road); Traffic flow (blue arrows): two lanes northwards then northeastwards along Fitzgerald Avenue (through and between the intersections with Kilmore Street and River Road and passing the northwestern side of worksite), two lanes southwestwards then southwards along Fitzgerald Avenue (passing the southeastern side of worksite and through and between the intersections with River Road and Avonside Drive).
Sourced from LINZ data, Crown Copyright reserved.

Stage 2 Works

  • Stage 2 works will start once Stage 1 works are complete. Stage 2 will take about one week to complete.
  • During Stage 2 a new manhole will be installed in the centre island south of the intersection. Refer to Map 3 for location of works.
  • Two-way traffic will be maintained on Fitzgerald Avenue across the Twin Bridges.
  • There will be no right turn across the intersection of Fitzgerald Avenue, Avonside Drive, and Kilmore Street during this stage of works.
  • We apologise for any inconvenience.
  • If you have any questions, please contact the Downer team.

Map 3: Stage 2
Map 3. Worksite (bright green): western side of the eastern side of Fitzgerald Avenue (between River Road and Avonside Drive), northern side of the southern side of Avonside Drive (adjacent east of Fitzgerald Avenue), centre of the southern side of the intersection of Fitzgerald Avenue with Kilmore Street and eastern side of the western side of Fitzgerald Avenue (adjacent south of Kilmore Street), southern side of the northern side of Kilmore Street (adjacent west of Fitzgerald Avenue); No right turn: from Fitzgerald Avenue into Kilmore Street, from Avonside Drive into Fitzgerald Avenue, from Fitzgerald Avenue into Avonside Drive, from Kilmore Street in to Fitzgerald Avenue; Traffic flow (blue arrows): two lanes northwards then northeastwards along Fitzgerald Avenue (through and between the intersections with Kilmore Street and River Road and passing the northwestern side of worksite), two lanes southwestwards then southwards along Fitzgerald Avenue (passing the southeastern side of worksite and through and between the intersections with River Road and Avonside Drive).
Sourced from LINZ data, Crown Copyright reserved.

The SCIRT programme is scheduled to finish at the end of 2016. After SCIRT has finished, the Christchurch City Council and New Zealand Transport Agency will continue to repair and rebuild the remaining earthquake damaged infrastructure.

Go the extra mile for businesses affected by rebuild roadworks.

For the location of road closures and major traffic impacts, refer to: Transport for Christchurch.

91%

We are 91% through the entire SCIRT programme.

General Information

  • Please contact Downer on 0800 400 310 if you have any specific access requirements that we need to consider e.g. large vehicle deliveries, rubbish collection, or planned works on your property.
  • There will be increased noise, dust and vibration levels associated with this work.
  • Works will have no planned impact on current power, telecommunication, water or gas services. However, the network is still fragile so please be prepared in case there is an unexpected service cut off.
  • All works are subject to favourable weather and on-site construction conditions.
  • Safety is our number one priority. Safety is your responsibility too. Stay clear and stay alert—keep children and pets at a safe distance from the worksite.

Need more information?

Call Downer on:
0800 400 310 between 8.30am and 5.00pm Monday to Friday
Email Downer:
[email protected]
Visit the SCIRT website:
www.strongerchristchurch.govt.nz

Start date: 
Mon, 27/06/2016
End date: 
Tue, 04/10/2016
Project numbers: 
11233