St Davids Street - Lyttelton - retaining walls - Completion

Printer-friendly version
What
Retaining wall repairs and storm water repairs
Where
St Davids Street
When
July 2015 to July 2016

Retaining wall repairs

Road open

SCIRT has left St Davids Street!

Since July 2015 we have completed repairs to five retaining walls, and installed a new stormwater main near 70 St Davids Street. We know that it hasn't been easy, and we would like to thank you for your patience over the last year.

Since last July we have used over 200 cubic metres of concrete, and over 50 soil nails and anchors to complete the five retaining walls.

Completed wall at 48 St Davids Street:
Photograph of wall.

Storm water main installation

The storm water main was so badly damaged in the earthquake that it was necessary to replace the entire length of the pipe, affecting residents we were working directly in front of, and in some cases on their private property. We started this tricky project in February 2016 and completed it in stages to minimise the impact on residents at any given time.

Storm water main installation:
Photograph of machinery installing storm water main.

Need more information?

Call Fulton Hogan on:
0800 277 34 34 (8.30am–5.00pm Monday–Friday)
Email Fulton Hogan:
[email protected]
Visit the SCIRT website:
www.strongerchristchurch.govt.nz

Start date: 
Tue, 19/07/2016
End date: 
Tue, 19/07/2016
Project numbers: 
10984
11063