Fitzgerald Avenue Twin Bridges - Richmond / Linwood / Central city - Bridge and roading repairs

Printer-friendly version
What
Bridge and roading repairs.
When
Starting Friday 19 August 2016 for about one month.

Map 1: Location of Works. Indicative Only. Sourced from LINZ data, Crown Copyright reserved. Roading repairs: Fitzgerald Avenue (adjacent north of the intersection with Kilmore Street/Avonside Drive), southeastern side of Fitzgerald Avenue (through the intersection with River Road); Kerb & channel and footpath repairs: southeastern side of Fitzgerald Avenue (through the intersection with River Road), northwestern side of Fitzgerald Avenue (opposite the southern side of the intersection with River Road); Handrail repairs: southern corner of River Road/Fitzgerald Avenue, and northwestern side of Fitzgerald Avenue (opposite the southern side of the intersection with River Road). Key. Roading repairs: purple; Kerb & channel and footpath repairs: orange; Handrail repairs: blue.

What we are doing

  • As you may know Downer, as part of SCIRT, is doing wastewater, bridge and roading repairs on the Fitzgerald Avenue Twin Bridges.
  • We will be conducting repairs to the bridge handrails and portions of the kerb and channel. The road and footpath that runs alongside the Twin Bridges will be resurfaced. See Map 1 for location of works.
  • This stage of work will begin on Friday 19 August, 2016 and take approximately one month to complete, subject to favourable weather and on-site conditions.

Traffic impacts

  • Two-way traffic on Fitzgerald Avenue will be maintained across the Twin Bridges.
  • The completion of some of these repairs will be done at night. You will receive prior notification before any change in traffic management occurs.
  • Access to properties and businesses will be maintained at all times.
  • Please be alert to changes in traffic management, follow signage and drive to the changed conditions.
  • Cones and signs are essential to allow our workers to safely complete the work. Traffic management is a legal requirement.
94%

We are 94% through the entire SCIRT programme.

What our work will look like

New footpaths:
Photo of smooth footpath.

Resurfacing the road:
Photo of truck tipping road resurfacing materials.

Kerb and channel repairs:
Kerb and channel freshly poured in place. Steel plates lie on the road shoulder.

Go the extra mile for businesses affected by rebuild roadworks.

General Information

  • Our standard work hours are Monday to Friday between the hours of 7.00am and 6.00pm. On occasion we may need to work outside these hours.
  • There will be increased noise, dust and vibration levels associated with this work.
  • Works will have no planned impact on current power, telecommunication, water or gas services. However, the network is still fragile so please be prepared in case there is an unexpected service cut off.
  • All works are subject to favourable weather and on-site construction conditions.
  • Safety is our number one priority. Safety is your responsibility too. Stay clear and stay alert—keep children and pets at a safe distance from the worksite.

Need more information?

Contact Downer on 0800 400 310 or [email protected]

Start date: 
Fri, 19/08/2016
Project numbers: 
11233